2 PSC Girder Bridges Structural Design – Manikgonj District (LGED)

Detail Structural Design, Estimate, Technical Specification and Standard Tender Document for 2 bridges under Manikgonj District. Bridges: 315m PSC Girder and 297m PSC Girder. Services include topographic survey, land acquisition plan, sub-soil investigation, structural design, BOQ, specification and tender documents. Funded by GOB.

Padma Bridge Approach Roads & Facilities Supervision Project

The Padma Multipurpose Bridge Project (PMBP), approximately 40 km south west of Dhaka, comprises a new fixed crossing of the Padma River in Bangladesh, which will consist of a bridge approximately 6.15km long, major river training works and approximately 13.6 km of approach roads and bridge-end facilities, including toll plazas, service areas and offices. The main bridge structure would carry a 4-lane highway, and have provisions for future installation of a single track dual guage rail line as well as other facilities including gas, power transmission and tele-communication lines. The main bridge is a two level steel truss superstructure with road traffic on the upper level and rail on the lower level acting compositely with a reinforced concrete deck slab. A brief description of the Main Bridge and River Training works (RTW) components of the project along with some schematic drawings is provided in Attachment 1. A pre-feasibility study of the proposed project was undertaken in 1999 comprising surveys, studies, preliminary designs, cost estimating, economic and traffic evaluation. This was followed by a feasibility study in 2003-2005 which comprised further studies and recommended the crossing be built at a location between Mawa and Janjira. This feasibility study formed the basis for the Government of Bangladesh (GoB) to proceed with the design and construction of the bridge. The project is divided into two phases: (i) Phase I- Detailed Design and Contract Procurement; and (ii) Phase II — Construction. The Design Consultants submitted the Final Design Report on July 5, 2011, which has been approved by the competent authorities. The bridge designs has been vetted by a separate consulting firm hired as the “Checking Engineers”. The Final Design of all i,e 5 contracts has been completed and Bid Documents prepared accordingly. The Government of Bangladesh has decided to take over/take up the project from its own fund. Accordingly 3(three) of the 5(five) contracts i,e contract no-3 Janjira approach road and selected bridge end facilities, contract no- 4 Mawa approach road & selected bridge end facilities and contract no- 5 service area-2 has been awarded to the contractors and works are going on accordingly. The current estimated total cost of the project is about US$ 2972.06 million. This document sets out the Terms of Reference (ToR) for Phase II, the construction phase of the project. The BBA intends to hire an international consulting firm to undertake overall construction supervision of the contract no-1 & contract no-2 i,e Main Bridge and River Training Works (RTW) covering the roles of the “Project Manager” and the “Engineer’s representatives”. A separate construction supervision consultant (CSC) has already been engaged for contract no 3, 4 & 5 i,e Janjira approach road and selected bridge end facilities, Mawa approach road & selected bridge end facilities and service area-2. All these activities will be financed by the Government of Bangladesh (GoB). Detailed Description of Actual Services provided by your staff: Consultancy services for construction supervision/project management are required to ensure that the construction of Main Bridge and River Training Works is implemented in an economical and efficient manner consistent with internationally accepted standard and practices with high standards of workmanship, specified quality of materials within the stipulated construction period and in conformity with the approved drawings and specifications, safeguard standards achieving objectives of the project with value for money. The main tasks and activities of the Construction Supervision Consultants (CSC), covering the pre-construction, construction and post construction stages of the Main Bridge and River Training Works would include, but not limited to, the following: A. Design Review and others Requirements. The CSC shall be required to undertake a thorough review of the all design documents prepared by the Design Consultants, within 60 days of the start of the contract, covering items listed below. At the end of this process, it will be assumed that the CSC is fully satisfied with the adequacy of the designs. i. Review the tender stage designs of the works completed earlier for adequacy and standards and provide comments thereon, if any; ii. Obtain Client’s approval, as necessary, for any major changes required in the designs already completed for bidding stage before finalization of Construction Drawings; iii. Incorporate all changes in design/drawings as agreed with the Client; iv. Carry out review of data and site investigations already carried out for all elements of the works;

Rajapara–Payra Port 4-Lane Road Project

Narrative Description of Project: Bangladesh’s external trade is growing on average at 9.2 percent per annum and by 2020th country’s total annual sea borne trade will be in the range of 75 to 80 million tones and 2.75 million twenty-foot equivalent unit (TEU) containers. These volumes are beyond the capacity of Bangladesh’s existing sea ports at Chittagong and Mongla. In particular, Chittagong presently handles around 92 percent of cargo and by 2020 it will have reached full operating capacity. Even a possible expansion of these two ports will not be sufficient to handle forecasted increases in trade volumes, and over the next decade this shortfall could reach around 50 percent of the country’s capacity needs. Given these constraints, the Government of Bangladesh has determined that the Rabnabad Channel at Kalapara Upazila in Patuakhali District is a naturally suitable place for constructing a seaport. This site has been subsequently named Payra Port. Payra Port is located on the West bank of the Rabnabad Channel, approximately 5 nautical miles upstream from harbour mouth. There are no restrictions regarding length and beam and the site with its outer anchorage can potentially cater to vessels with 14.5 metre draught. Considering the handling of future trade volume and export/import growth, Govt. of the People’s Republic of Bangladesh decided to build a new sea port and an Act was passed on National Parliament on 05 Nov 2013. Honorable Prime Minister inaugurated 3rd sea port at Lalua Union, Kalapara Upazila of Patuakhali district on 19 Nov 2013. Description of Actual Services Provided by your staff in the assignment: The work consists of construction supervision of RCC Road, Bridge/Culvert and related structures in accordance with the highest standards of the engineering profession and the applicable standards of PPA. The Consultant will render services under the terms of reference (ToR) but not limited to the following: i) Review road and structural design ii) Site Supervision and witness of Testing and Commissioning iii) Project Management The detailed scope of works is described below: i) Review sub-soil investigation report and other related data ii) Review road and structural design iii) Construction supervision of RCC Road, Structures and other related Structures iv) Project Management and Contract Administration v) Arrange monthly meeting

Sylhet–Tamabil–Jaflong 4-Lane Highway Project (N2)

Narrative description of Project: The Design Review Consultant (DRC) has reviewed the Detailed Design of Sylhet-Tamabil Road which was done under Technical Assistance for Sub-Regional Road Transport Project Preparatory Facility (TA-SRTPPF) by finalizing the following tasks: Task-1: Review and update the Feasibility /other studies and procurement documents for the Sylhet Tamabil Road Section.Task-2: Complete review of the Design (including revisiting the designs of high embankment sections, soft grounds, drainage, crossing bazar, villages and road cuts). Review pavement designs considering large number of heavy trucks and proposing PMB in top bituminous layer (wearing course and base course) with detailed specification and methodology. Task- 3: Design of toll plaza. Key features of the project are given below: § Total Road length 56.1km, divided 4 lane road with service lane both sides, main carriageway lane Width 7.3m, service lane Width 5.5m § Toll Plaza No.: 2; 10 lane central toll and 6 lane Surma bridge toll § Box Culverts: 48, under pass: 2, Junction: 7, Bazar Area 9, FOB: 17 Three types of Bridges, Type A, B and C with top width respectively 15.3m, 30.6m and 7.3m. Type A and Type C are built beside existing bridges and type B are standalone new bridges. Typical Pile dia 1.2m. For 411m Surma bridge 1.5m pile dia used. Total 20 Bridges (13 type A+C and 7 type B), Total bridge length = 2223m.

Cumilla–Brahmanbaria 4-Lane Highway Project (GDP-04)

The Government of Bangladesh (GoB) has decided to upgrade the existing Cumilla (Mainamati)-Brahmanbaria (Dharkhar) National Highway (N-102) to a 4-Lane National Highway with safety features including a separate lane for slow-moving vehicular traffic (SMVT) on both sides. thereon with the fund (for civil works) jointly invested by the GoB and the Indian Government (GOILOC03). The length of the road is 54.00 km, starting from Cumilla (Moinamati) and ending at Dharkhar, Brahmanbaria. The GoB has allocated public funds for engaging a consulting firm for the Design Review and updates of Highway, Bridges, Flyover etc., Assisting Procurement Process and Supervision of highway Construction works (Length 54.00 km). The Project will include upgrading of existing Cumilla (Mainamati)-Brahmanbaria (Dharkhar) National Highway (N-102) to a 4-Lane Highway, including service lanes at both sides through two packages of civil works contract. The construction works consist of the upgradation/construction of 54.00 kilometers of four-lane National Highway with international standards, of which 49.53 kilometers flexible pavement, 4.47 kilometers are rigid pavement, 14 nos. Bridges having a length of 1218.44 meters, 01 no. Flyover having length of 1030.224 meters, 02 nos. underpass having length of 20.00 meters, 50 nos. RCC Box culvert has a total length of 396.30 meters, 12 nos. Foot Over Bridges has a length of 438.91 meters and Construction of 680 sq.m. office building etc. The-feasibility study, LA & Resettlement plan, detailed designs have been prepared in 2015 through Technical Assistance for Subregional Road Transport Project Preparatory Facility, implemented by RHO, which requires review. Objectives of the Assignment The main objectives of the Consultancy services are – i. To supervise comprehensively the project implementation activities carried out by the contractor(s) to ensure complete compliance with the drawings, technical specifications, and various stipulations in the contract documents. ii. To supervise & monitor safeguards implementation including health and safety activities associated with the project. iii. To monitor & supervise environmental & social development safeguards associated with the project. iv. Other services as per instruction of the employer. Scope of Services The Consultant will (i) Prepare (if required), review the detailed design for the project road already prepared by the RHD and preparation and review of Flyover, intersection, Bridge/Culvert design, (ii) provide procurement/contract-related supports, (iii) provide construction supervision to civil works, and (iv) provide other technical support including traffic management and road safety plan. In addition to the above services, the Consultant will undertake maintenance quality checks for the project road with regard to the technical, contractual, and financial aspects of the project implementation.